GIA-General-(Developmental Works)

Sl.No Name of work A/A & E/S No. and Amount Work Order No. Name of Agency Sub Division Work Type Stipulated date of commencement Stipulated date of Completion Physical Progress Remarks Work Status
1 Construction of Compound wall at Ayyapan Temple under Zilla Parishad, South Andaman. Memorandum No. 19-97/Genl/PLZP/2024/1749 dated 13.02.2024 Rs. 14,92,923/- EE/SA/ZP/2023-2024/04 dated 21.06.2024 agt. Amount Rs. 12,75,084/- K. Kannan Govt. Contractor, Hut Bay, Little Andaman. SD-4 GIA-General(Development Works) 06.07.2024 05.12.2024 100% Work completed. 1st & final bill with DA/ZP/SA Completed Works
2 Painting at Chidambaram Park under ZP, Hut Bay (Little Andaman). Memorandum No. 19-96/Genl/PLZP/2024/1750 dated 13.02.2024 Rs. 10,22,559/- No. 38/Adhyaksh/ZP/2023-2024 dated 08.03.2024 Rs. 6,34,437/- Ganga Un-Employed Construction Co-operative Society SD-4 GIA-General(Development Works) 08.03.2024 07.09.2024 100% Work Completed. 1st and final bill submitted to DA/ZP/SA on dated 24.04.2024 Completed Works
3 C/o. C.C. Drain on C.C. Road side from Shri. Vinod Singh house to Rajendran Pan Shop at W.No. 04 Campbell Bay, Govind Nagar by Zilla Parishad, South Andaman. No. 20-82/Genl/PL/ZP/2023/1012 dated 27/04/2023 Rs. 9,68,585.00 12/Adhyaksh/ZP/2023-24 Pragathi Un Employed Multipurpose Co-operative Society Ltd.' Govind Nagar, Campbell Bay. SD-4 GIA-General(Development Works) 19.07.2023 18.01.2024 100% Work completed Completed Works
4 Construction of CC platform flag post, window grills and providing and installation of pump including electric wiring and PVC pipeline at ZPVKV, ferrargunj, south andaman 15-603/Edu/PL/ZP/2024-1952 dated 15.03.2024 Rs. 10,48,504/- 43/Adhyaksh/ZP/2023-24 dated 15.03.2024 Rs. 10,31,814/- Lakshya Construction Co-operative Society Ltd, Ferrargunj, South Andaman SD-2 GIA-General(Development Works) 15.03.2024 15.04.2024 100% Work Completed. Bill submitted to EE/ZP/SA for payment. Completed Works
5 Facelifting of vegitable market at ferrargunj under Zilla Parishad, South Andaman 15-600/Genl/PL/ZP/2023-1930 dated 07.03.2024 Rs. 11,64,063/- 36/Adhyaksh/ZP/2023-24 dated 07.03.2024 M/s Kingdo Construction Co-operative Society Ltd. SD-2 GIA-General(Development Works) 07.03.2024 07.04.2024 100% Work completed. Bill submitted to EE/ZP/SA for payment. Completed Works
6 C/o Community hall at Mile Tilak under Ferrargunj Gram Panchayat by Zilla Parishad, South Andaman. 15-567/Genl/PL/ZP/ 2023/750 dated: 25.01.2023 Rs. 78,25,881/- EE/SA/ZP/2023-24/4 Rs. 59,21,375.13 M/s A P Husainar Rehmaniya Masjid Road, Bambooflat, South Andamanb PH: 9933212806 SD-2 GIA-General(Development Works) 11.04.2023 11.04.2024 100% Work completed. 3rd and final bill under process. Completed Works
7 Removal of Nallah gravel from the land situated at Bimblitan near Karupuswamy temple under Port Blair Tehsil. 15-560/RS/PL/ZP/2020/365 dated 01/07/2020 W.O. No. 28/Adhyaksh/ZP/2023-24 Rs. 3,38,000.00 Durga Unemployed Co-operative Society Ltd, Sippighat SD-1 GIA-General(Development Works) 12/01/2024 11/03/2024 100% Work Completed Completed Works
8 Construction of RCC Pedestal for fixing statue & development of adjacent area in the campus of Zilla Parishad Bhawan under Zilla Parishad, South Andaman. 14-587/Genl/PL/ZP/2023/1563 dated 15.12.2023 23/Adhyaksh/ZP/2023-24 dated 15.12.2023 Rs. 11,32,134 Wisdom Construction Co-operative Society Ltd., Ferrargunj. SD-1 GIA-General(Development Works) 15.12.2023 14.01.2023 100% Work Completed Completed Works
9 Construction of Community Hall at Farm Tikrey SW: Upto Plinth level 79/GENL/PL/ZP/2014/623 Dt.21/07/2014. RS. 74,45,911/- EE/SA/ZP/2016-2017/14 DT. 30.01.2017 RS. 60,51,321/- Shri Montu Mandal, Govt. Contractor, V.K.Pur, Littel Andaman Prothrapur GIA-General(Development Works) 2014-2015 Completed Works
10 Construction of Community Hall at Farm Tikrey SW: Upto Plinth level 79/GENL/PL/ZP/2014/623 Dt.21/07/2014. RS. 74,45,911/- EE/SA/ZP/2016-2017/14 DT. 30.01.2017 RS. 60,51,321/- Shri Montu Mandal, Govt. Contractor, V.K.Pur, Littel Andaman Prothrapur GIA-General(Development Works) 2014-2015 Completed Works
11 Repair and Maintenance of Community Hall near Radha Gobind Temple at Neil Kendra, Neil Island by Zilla Parishad No. 14-420/Gen/PL/ZP/2012/617 Rs. 3,77,871/- EE/ZP/SA/2013-14/19 dt. 17/06/2013 Shri. Amar Lal Das, Govt. Contractor, Neil Island. Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
12 C/o CC Footpath/Road from main road to Anil and Ajit house Tushnabad under Gram Panchayat, Tushnabad by Zilla Parishad, South Andaman. 15-468/Genl/PL/ZP/15/68 Rs.5,15,417/- 55/Adhy/ZP/2015-2016 Rs.5,63,749/- M/s Dweep Development Multipurpose Co.Op. society Ltd.Tushnabad Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
13 C/o. Compound wall around Christian burial ground at Ward no.05 under Gram Panchayat Bambooflat by Zilla Parishad, South Andaman 15-504/Genl/PL/ ZP/2016/1190 dt. 01.12.16 Rs.26,25,986/- EE/SA/ZP/2016-2017/23 dt, 19.06.2017 Rs. 34,42,801/- A. R. Construction Govt. Contractor & order Supplier, Mathura. Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
14 Construction of community hall at Tsunami Shelter at Mithakhari-06 under Gram Panchayat, Mithakhari by Zilla Parishad. 15-541/Genl/PL/ZP/2017/954 dt.22.09.2017 Rs. 39,06,075/- EE/SA/ZP/2017-2018/21 Rs. 45,57,843/- M/s SPR Construction,Govt. Contractor, Stewartgunj,South Andaman. Little Andaman GIA-General(Development Works) 2014-2015 Completed Works
15 C/o R.C.C Retaining wall and culvert in front of Pentacostal Church at Brindaban W.No 05 under Zilla Parishad, South Andaman 15-436/GENL/PL/ZP/2014/618 DT. 21.07.2014 RS. 37,28,372 EE/SA/ZP/2016-17/16 DT. 30.01.2017 RS. 44,17,280/- K.T. Manoj Govt. Contractor, Wright Myo Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
16 C/o C.C. Drain along nallah from existing culvert near A Kutty’s house upto Wimberlygunj School at W.No. II under Wimberlygunj Gram Panahcyat 15-379/Genl/PL/ZP/12/287 dt. 04.04.12 - Rs. 26,86,341 EE/SA/ZP/2013-14/39 Shri A. Abdul Aziz, Govt. Contractor & Order Supplier, Stewartgunj Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
17 C/o C.C drain cum retaining wall between house of Shri.M.A Anvar Hussain to M.A Kalliappan house at Rajeev Nagar W.No.1 under Gram Panchayat Shore Point by Zilla Parishad 15-407/Genl/PL/ZP/ 2012/1115 dt.20-10-12 Rs.10,16,422/- W.O.No. 06/ZP/Adhy./2012-13 dt. 11.12.12. M/S. Rising Construction Co-operative Socxiety Ltd., Hopetown Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
18 C/o C.C Footpath with drain & retaining Wall from Shri Ramamoorthy’s house to Shri Laxman Rao’s house at Ward No. 10 by Zilla Parishad, South Andaman 15-411/Genl/PL/ZP/ 2012/1272 dt.13-12-12 Rs. 5,50,647/- 19/ZP/Adhy/2013-14 dt. 09/07/2013 M/s Anasuya Const. Coop-Society, Ltd, Shorepoint Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
19 Construction of Mini Stadium at Choudhury Pahad under Shorepoint Panchayat by Zilla Parishad. 15-263/Genl/PL/ZP/06/1604 dt. 02.11.07 - Rs. 53,45,356.00 EE/SA/ZP/2008-09/55 dt. 26.12.2008 Shri Swapan Sarkar, Govt. Contractor, Nayagaon, Port Blair Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
20 Construction of Retaining wall near Shri Vallaiah’s house at Ward No. 04, Bambooflat under Zilla Parishad, South Andaman. 15-363/Genl./PL /ZP/2011/844 dt. 20.09.2011 – Rs. 5,62,967/- EE/ZP/SA/2012-13/ 19 dt. 11/07/2012 M/s. P.A.S. Construction, Stewartgunj Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
21 Renovation, maintenance, painting and fencing with grill gate of Mahila Mondal at Guptapara - II by Zilla Parishad, South Andaman. 15-402 /Genl./PL/ZP/2012 /1275 dt. 13.12.12. Rs. 2,09,285/- W.O. No. 15/ZP/Adhy/ 2013-14 dt. 23.05.13 M/s Sagar Construction Co-operative Society Ltd., Wandoor Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
22 C/o Multipurpose Hall at Wandoor near Gram Panchayat Bhawan , Humphrygunj by Zilla Parishad SW: Providing, Installation of Internal & Electrical electrification 15-413/Genl. /PL/ZP /2012 /1276 dated 13.12.12 – Rs. 3,69,995/- EE/SA/ZP/13-14/02 Dt. 05.04.13 M/s. M.K.Construction, Stewartgunj Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
23 Construction of Passenger shed at Humphrygunj under Humphrygunj Panchayat by Zilla Parishad, South Andaman. 15-390/Genl./PL/ZP/ 12/616 Dt.22.06.12 -Rs.1,91,059/- EE/SA/ZP/12-13/33 Dt.06-11-12 M/s. Shyamal Construction Herbertabad Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
24 Construction of Multipurpose Hall at Wandoor near Gram Panchayat Bhawan Humfrygunj under Zilla Parishad, South Andaman. 15-302/RR/PL/ZP/08/ 1497 dt.16.10.07 - Rs.63,69,317/- EE/SA/ZP/08-09/42 dated 15.10.2008 M/s Mallick Enterprises, Govt. Contractor, Port Blair Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
25 Renovation, Maitenance, Painting and fencing with grill gate of Mahila Mondal at Manjery-II and Zilla Parishad, South Andaman. 15-405/Genl/PL/ZP/12/1277 Dt.13/12/12 Rs.1,32,716/- W.O.No-14/ZP/Adhy/13-14 Dt.23/05/2013 M/s Islander Unemployed Youth Co-operative Society Ltd, Nayasahar Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works
26 C/o C.C drain from Shri Swaminathan house to Shri Charminar house at W. No 9 under Bambooflat Panchayat by Zilla Parishad 15-303/GENL/PL/2007/712 DT. 01.06.2009 RS. 42,93,693/- EE/SA/ZP/14-15/02 DT. 24.04.2014 RS. 102,73,601/- A R Construction Govt. Contractor & order supplier Mathura Ferrargunj GIA-General(Development Works) 2014-2015 Completed Works