1 |
Renovation of 04 Nos Cottage at Zilla Parishad Niwas, Port Blair under Zilla Parishad, South Andaman. |
14-553/MS/PL/ZP/ 2020/607 dt. 07.12.2020 Rs.29,88,169/- |
-- |
M/s. Anand Traders & Construction Near Range Office, Bathubasti, South Andama |
SD-1 |
GIA-General(Development Works) |
2021-2022 |
Completed Works |
2 |
Construction of Community Hall at Farm Tikery, Hut Bay., Sub Work : Internal Electrification at Community Halll at Farm Tikrey |
19-92/Genl/PL/ZP /2018/675 dated 24th September, 2018. Rs.89,42,405/- (Revised Estimate) |
EE/SA/ZP/2018-19/35 dated: 09.01.2019 Rs.2,22,260/- |
M/s Kathir Marketing Service Junglighat South Andaman |
SD-4 |
GIA-General(Development Works) |
2019-2020 |
Completed Works |
3 |
Construction of Community Hall at Farm Tikery, Hut Bay. Sub work : Upto Plinth Level |
19-92/Genl/PL/ZP /2018/675 dated 24th September, 2018. Rs.89,42,405/- (Revised Estimate) |
EE/SA/ZP/2014-15/13 Dated: 30.01.2015 Rs.11,10,221/- |
Shri. Mantu Mondal, V.K. Pur, Hut Bay, South Andaman. |
SD-4 |
GIA-General(Development Works) |
2015-2016 |
Completed Works |
4 |
Construction of Community Hall at Farm Tikery, Hut Bay.
Sub work : Above Plinth Level |
19-92/Genl/PL/ZP /2018/675 dated 24th September, 2018. Rs.89,42,405/- (Revised Estimate) |
EE/SA/ZP/2016-17/14 dated:22.11.2016 Rs.60,51,321/- |
Shri. Amal Das Govt contractor, Little Andaman |
SD-4 |
GIA-General(Development Works) |
2016-2018 |
Completed Works |
5 |
Construction of Cultural Stage with Toilet Block in Netaji Play Ground at Ward No.7 at R.K Pur Under R.K Pur Zilla Parishad, Little Andaman. |
No.19-87/Genl /Pl/ZP/2018/541 dated 14.08.2018 Rs.26,70,309/- |
-- |
Shri. Mantu Mondal, V.K. Pur, Hut Bay, South Andaman. |
SD-4 |
GIA-General(Development Works) |
2019-2020 |
Completed Works |
6 |
Construction of retaining Wall with drain from Shri Vallab Rao's house to Shri Bhagat Ram's house at W. No.3 Bambooflat by Zilla Parishad |
15-434/Genl/ PL/ZP/2013 /619 dt.21-07-2014 Rs.33,96,818/- |
-- |
M/s. Thirumala Construction, Govt. Contractor, Haddo |
SD-3 |
GIA-General(Development Works) |
2015-2016 |
Completed Works |
7 |
Construction of community Hall at Tsunami Shelter at Mithakhari-06 under Gram Panchayat, Mithakhari by Zilla Parishad. |
15-541/Genl/PL /ZP/2017/954 dt.22.09.2017 Rs. 39,06,075/- |
-- |
M/s SPR Construction, Govt. Contractor, Stewartgunj,South Andaman |
SD-2 |
GIA-General(Development Works) |
2018-2019 |
Completed Works |
8 |
C/o Multipurpose Community Hall under Gram Panchayat, Namunaghar by Zilla Parishad, South Andama |
15-541/Genl/PL /ZP/2020/349 dt. 24-06-2020 Rs.56,49,502/- |
-- |
Shri A. Palani, Govt. Contractor, Bambooflat, South Andaman. |
SD-2 |
GIA-General(Development Works) |
2021-2022 |
Completed Works |
9 |
Construction of 02 Nos. Anganwadi one at Ramnagar and another at Laxmanpur at Neil Island under Zilla Parishad (Balance work) |
14-455/Genl/ PL/ZP/2014-624 Dated 21/07/2014 Rs. 59,89,512/ |
-- |
Shri. A.S. Rathnam, Govt. Contractor, Bathu Basti, Garacharma Post |
SD-1 |
GIA-General(Development Works) |
2016-2017 |
Completed Works |
10 |
Construction of Community Hall at Farm Tikrey SW: Upto Plinth level |
79/GENL/PL/ZP/2014/623 Dt.21/07/2014. RS. 74,45,911/- |
EE/SA/ZP/2016-2017/14 DT. 30.01.2017 RS. 60,51,321/- |
Shri Montu Mandal, Govt. Contractor, V.K.Pur, Littel Andaman |
Prothrapur |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
11 |
Construction of Community Hall at Farm Tikrey SW: Upto Plinth level |
79/GENL/PL/ZP/2014/623 Dt.21/07/2014. RS. 74,45,911/- |
EE/SA/ZP/2016-2017/14 DT. 30.01.2017 RS. 60,51,321/- |
Shri Montu Mandal, Govt. Contractor, V.K.Pur, Littel Andaman |
Prothrapur |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
12 |
Repair and Maintenance of Community Hall near Radha Gobind Temple at Neil Kendra, Neil Island by Zilla Parishad |
No. 14-420/Gen/PL/ZP/2012/617 Rs. 3,77,871/- |
EE/ZP/SA/2013-14/19 dt. 17/06/2013 |
Shri. Amar Lal Das, Govt. Contractor, Neil Island. |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
13 |
C/o CC Footpath/Road from main road to Anil and Ajit house Tushnabad under Gram Panchayat, Tushnabad by Zilla Parishad, South Andaman. |
15-468/Genl/PL/ZP/15/68 Rs.5,15,417/- |
55/Adhy/ZP/2015-2016 Rs.5,63,749/- |
M/s Dweep Development Multipurpose Co.Op. society Ltd.Tushnabad |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
14 |
C/o. Compound wall around Christian burial ground at Ward no.05 under Gram Panchayat Bambooflat by Zilla Parishad, South Andaman |
15-504/Genl/PL/ ZP/2016/1190 dt. 01.12.16 Rs.26,25,986/- |
EE/SA/ZP/2016-2017/23 dt, 19.06.2017 Rs. 34,42,801/- |
A. R. Construction Govt. Contractor & order Supplier, Mathura. |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
15 |
Construction of community hall at Tsunami Shelter at Mithakhari-06 under Gram Panchayat, Mithakhari by Zilla Parishad. |
15-541/Genl/PL/ZP/2017/954 dt.22.09.2017 Rs. 39,06,075/- |
EE/SA/ZP/2017-2018/21 Rs. 45,57,843/- |
M/s SPR Construction,Govt. Contractor, Stewartgunj,South Andaman. |
Little Andaman |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
16 |
C/o R.C.C Retaining wall and culvert in front of Pentacostal Church at Brindaban W.No 05 under Zilla Parishad, South Andaman |
15-436/GENL/PL/ZP/2014/618 DT. 21.07.2014 RS. 37,28,372 |
EE/SA/ZP/2016-17/16 DT. 30.01.2017 RS. 44,17,280/- |
K.T. Manoj Govt. Contractor, Wright Myo |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
17 |
C/o C.C. Drain along nallah from existing culvert near A Kutty’s house upto Wimberlygunj School at W.No. II under Wimberlygunj Gram Panahcyat |
15-379/Genl/PL/ZP/12/287 dt. 04.04.12 - Rs. 26,86,341 |
EE/SA/ZP/2013-14/39 |
Shri A. Abdul Aziz, Govt. Contractor & Order Supplier, Stewartgunj |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
18 |
C/o C.C drain cum retaining wall between house of Shri.M.A Anvar Hussain to M.A Kalliappan house at Rajeev Nagar W.No.1 under Gram Panchayat Shore Point by Zilla Parishad |
15-407/Genl/PL/ZP/ 2012/1115 dt.20-10-12 Rs.10,16,422/- |
W.O.No. 06/ZP/Adhy./2012-13 dt. 11.12.12. |
M/S. Rising Construction Co-operative Socxiety Ltd., Hopetown |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
19 |
C/o C.C Footpath with drain & retaining Wall from Shri Ramamoorthy’s house to Shri Laxman Rao’s house at Ward No. 10 by Zilla Parishad, South Andaman |
15-411/Genl/PL/ZP/ 2012/1272 dt.13-12-12 Rs. 5,50,647/- |
19/ZP/Adhy/2013-14 dt. 09/07/2013 |
M/s Anasuya Const. Coop-Society, Ltd, Shorepoint |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
20 |
Construction of Mini Stadium at Choudhury Pahad under Shorepoint Panchayat by Zilla Parishad. |
15-263/Genl/PL/ZP/06/1604 dt. 02.11.07 - Rs. 53,45,356.00 |
EE/SA/ZP/2008-09/55 dt. 26.12.2008 |
Shri Swapan Sarkar, Govt. Contractor, Nayagaon, Port Blair |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
21 |
Construction of Retaining wall near Shri Vallaiah’s house at Ward No. 04, Bambooflat under Zilla Parishad, South Andaman. |
15-363/Genl./PL /ZP/2011/844 dt. 20.09.2011 – Rs. 5,62,967/- |
EE/ZP/SA/2012-13/ 19 dt. 11/07/2012 |
M/s. P.A.S. Construction, Stewartgunj |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
22 |
Renovation, maintenance, painting and fencing with grill gate of Mahila Mondal at Guptapara - II by Zilla Parishad, South Andaman. |
15-402 /Genl./PL/ZP/2012 /1275 dt. 13.12.12. Rs. 2,09,285/- |
W.O. No. 15/ZP/Adhy/ 2013-14 dt. 23.05.13 |
M/s Sagar Construction Co-operative Society Ltd., Wandoor |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
23 |
C/o Multipurpose Hall at Wandoor near Gram Panchayat Bhawan , Humphrygunj by Zilla Parishad SW: Providing, Installation of Internal & Electrical electrification |
15-413/Genl. /PL/ZP /2012 /1276 dated 13.12.12 – Rs. 3,69,995/- |
EE/SA/ZP/13-14/02 Dt. 05.04.13 |
M/s. M.K.Construction, Stewartgunj |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
24 |
Construction of Passenger shed at Humphrygunj under Humphrygunj Panchayat by Zilla Parishad, South Andaman. |
15-390/Genl./PL/ZP/ 12/616 Dt.22.06.12 -Rs.1,91,059/- |
EE/SA/ZP/12-13/33 Dt.06-11-12 |
M/s. Shyamal Construction Herbertabad |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
25 |
Construction of Multipurpose Hall at Wandoor near Gram Panchayat Bhawan Humfrygunj under Zilla Parishad, South Andaman. |
15-302/RR/PL/ZP/08/ 1497 dt.16.10.07 - Rs.63,69,317/- |
EE/SA/ZP/08-09/42 dated 15.10.2008 |
M/s Mallick Enterprises, Govt. Contractor, Port Blair |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
26 |
Renovation, Maitenance, Painting and fencing with grill gate of Mahila Mondal at Manjery-II and Zilla Parishad, South Andaman. |
15-405/Genl/PL/ZP/12/1277 Dt.13/12/12 Rs.1,32,716/- |
W.O.No-14/ZP/Adhy/13-14 Dt.23/05/2013 |
M/s Islander Unemployed Youth Co-operative Society Ltd, Nayasahar |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |
27 |
C/o C.C drain from Shri Swaminathan house to Shri Charminar house at W. No 9 under Bambooflat Panchayat by Zilla Parishad |
15-303/GENL/PL/2007/712 DT. 01.06.2009 RS. 42,93,693/- |
EE/SA/ZP/14-15/02 DT. 24.04.2014 RS. 102,73,601/- |
A R Construction Govt. Contractor & order supplier Mathura |
Ferrargunj |
GIA-General(Development Works) |
2014-2015 |
Completed Works |