Sl.No Name of work A/A & E/S No. and Amount Work Order No. Name of Agency Sub Division Work Type Stipulated date of commencement Stipulated date of Completion Physical Progress Remarks Work Status
1 Construction of CC road from S. Lok Das house to Sea shore at W.No 07 Govind Nagar by Zilla Parishad. Memo No.20-88/RR/PL/ZP/2024/1688 Dt. 29/01/2024 sanctioned Rs. 29,89,878/- EE/SA/ZP/2024-25/02 dt. 21.06.2024 Rs. 24,89,672/- Shri. Kulvinder Singh Govt. Contractor, Campbell Bay SD-4 Roads and Bridges 06.07.2024 02.01.2025 5% Demarcation has to be done by Revenue Departement. Letter issued to the Tehsildar vide letter No. 1-59/AE/SD-IV/SA/ZP/2023-24/14 dt. 01.07.2024. Material dumped at site. Ongoing Works
2 Construction of RCC Retaining wall backside Narender house at RPRS Colony W.No.06, Campbell Bay by Zilla Parishad, South Andaman. Memo No.20-87/RR/PL/ZP/2024/1687 Dt. 29/01/2024 sanctioned Rs. 11,43,377/- 45/Adhyaksh/ZP/2023-2024 Rs. Dt. 15/03/2024 Rs. 10,08246/- Prgathi un-employed multipurpose Co-operative society Ltd at Campbell Bay. SD-4 Roads and Bridges 15/03/2024 15/06/2024 Nil Due to imposition of MCC, this work was held up, after MCC work has been not started. Stipulated dt. of completion is also lapsed on 15.06.2024. Ongoing Works
3 C/o CC Drain from M. Shankar Shelter to Sriram Shelter at Shastri Nagar under Panchayat Laxmi Nagar Campbell Bay by Zilla Parishad, South Andaman. Memo No. 20-86/RR/PL/ZP/20223/1176 Dt..27/07/2023 sanctioned Rs. 17,09,919/- EE/SA/ZP/2023-24/23 dated: 18/01/2024 Rs.19,13,940.00/- Kulvinder Singh Govt. Contractor. SD-4 Roads and Bridges 02/02/2024 01/05/2024 Nil work not yet started. Before commencement of work, land to demarked by revenue Department. Ongoing Works
4 Earth filling and CC Road Culvert from Kartar Singh at Ward No. 03 Govind Nagar (Campbell Bay). Mwmo No. 20-81/RR/PL/ZP/2023/1025 dt. 01.05.2023 Rs. 15,78,124/- EE/ZP/SA/2023-24/12 dated 16/06/2023 Rs.13,63,263.30 M K S Construction Bathu Basti, Port Blair SD-4 Roads and Bridges 07.01.2023 31.12.2023 40% In progress Ongoing Works
5 Addition and Alteration to the existing open prayer hall at Zilla Parishad Vivekananada Kendra Vidyalaya, Shore Point under Zilla Parishad, South Andaman. No. 15-598/Edu/PL/ZP/2024/1908 dt. 08.03.2024 sanctioned? . 16,18,048/- EE/SA/ZP/2024-2025/24 dt 04.09.2024 ? 11,10,604.90 M/s Crescent Construction, Govt. Contractor Goal Ghar, South andaman. SD-3 Roads and Bridges 18.09.2024 16.03.2025 65% flooring work in progress Ongoing Works
6 Repair and maintenance of village road Shri. L Tata Rao's house and Shri. L Mohan Rao's house at North Bay Ward No. 02, under Hopetown, GP by Zilla Parishad, South Andaman. No. 15-586/RS/PL/ZP/2023/1568 dt. 15.12.2023 sanctioned Rs. 23,21,254/- EE/SA/ZP/2024-25/14 dated. 29.08.2024 Shri. S. Selvraju, Govt. Contractor, Near Ramkrisen store, Shore Point. SD-3 Roads and Bridges 13.09.2024 11.05.2025 Nil Work not start. Ongoing Works
7 Repair and maintenance of North Bay village road to William house via Chandrawathi house to Jamuna house and Kathreena house including Retaining wall and Drain by Zilla Parishad, South Andaman 15- 590/ RR(NP)/PL/ZP/2023/1837 dated:01.03.2024 Rs.27,16,017/- EE/SA/ZP/2024-25/12 dated 29.08.2024, Rs. 26,76,784/- Shri. S. Selvraju, Govt. Contractor, Near Ramkrisen store, Shore Point. SD-3 Roads and Bridges 13.09.2024 10.05.2025 Nil Work not start. Ongoing Works
8 Renovation of Rural Road from Shri. K.T. Pillai house to Shri. B. Ummer house at Wright Myo-III under Zilla Parishad, South Andaman (Revised Estimate). 15- 484/ RR/PL/ZP/2023/793 dated:14/02/2023 ?.15,90,592/- EE/SA/ZP/2023-2024/21 dated: 21/12/2023 M/S Balaji Enterproses, MG Road, Middle Point, Port Blair SD-3 Roads and Bridges 05/01/2024 02/07/2024 - Work not yet Started. Ongoing Works
9 Construction of Village Road (Black Top Road) from existing village road to Shri. K.P. Mani house at Hope Town -02 by Zilla Parishad, South Andaman (L-180.00 Mtrs.) (Balance work) Sub work :- C/o. C.C. Road for a length 60.00 mtrs. 15-589/RS/PL/ZP/2023/1156 dated: 18/07/2023 ?. 9,74,684/- 13/Adhyaksh/ZP/2023-2024 dt: 08/10/2023 ?. 8,30,485/- Rising Construction Co-operative Society SD-3 Roads and Bridges 09.08.2023 12.07.2023 - Due to Non-availability of Quarry Product work not yet started. Ongoing Works
10 Renovation of black top road from Subramanium house to markaz school at ward no. kanyapuram -04 by ZPSA. 15-566/RS/PL /ZP/2023/770 dated 02.02.2023 EE/ZP/SA/2023-2024/11 dated 19.05.2023 ?.23,83,412.50/- Shuvam Construction Mathura, Ferrargunj, south Andaman SD-3 Roads and Bridges 06.02.2023 12.02.2023 Nil The site has handed over to contractor on 30.06.2023. Work held up by the contractor due to non availability of quarry products. Ongoing Works
11 Repair and maintenance of C.C Road from ATR to Shree Ayyappa Temple, Coffee Bagicha under Humfrygunj Panchayat Zilla Parishad, South Andaman (Non Plan) 599/RS(NP)/PL/ZP/2024/1821 dt. 29.02.2024 EE/SA/ZP/2024-25/11 dt 05.07.2024 ?. 14,69,999.70/- M/s. Anand Traders & Construction, Govt. contractor, Garacharma. SD-2 Roads and Bridges 23.07.2024 19.11.2024 75% Work in progress. Due to rain the work is hampered miserabely. Ongoing Works
12 C/o. black top road from main road to Tapas Banik house via Ravi Banik house at Manglutan-I (Guptapara) by Zilla Parishad, South Andaman. 15-579/RS/PL/ZP/2023/987 dated 07.04.2023 ?. 18,93,842/- EE/SA/ZP/2023-24/17 ? 12,13,349/- M/s KMS Construction Mathura, South Andaman. SD-2 Roads and Bridges 06.09.2023 03.03.2024 2% I st & 2nd Show cause notice issued to the executing agency vide No. 4-1(1158)/RS/FG/EE/SA/ZP/2022-23/118 dt. 17.05.2024 & vide No. 4-1(1158)/RS/FG/EE/SA/ZP/2022-23/225 dt. 24.06.2024 (Work Cancelled) Ongoing Works
13 C/o. Black top road and drain near CIARI, NH-4 to D. Toppo house at Chouldari-03 under Zilla Parishad. 15-574/RS/PL/ZP/2023/7072 dated 07.06.2023 ?. 18,89,743/- EE/SA/ZP/2023-24/25 ? 14,54,776/- M/s PAS Construction Govt. Contractor & Truck Owner, Stewart Gunj, South Andaman PH. 9933263426 SD-2 Roads and Bridges 29.02.2024 28.08.2024 30% Drain work upto 60.00mtr length completed. Present work held up due to continuous flow of rain water through the working site. Ongoing Works
14 C/o Black top road from Muthu house to Dhinakaran house including retaining wall and drain at Manpur-I by Zilla Parishad, South Andaman. 15-516/RR/PL /ZP/2016/947 dt. 20-11-2019 ? 66,98,696/- EE/SA/ZP/2020-21/08 ? 62,42,559/- M/s City Construction Company C/o Hotel Anbu, near Govt. Polytechnic, Dollygunj. Ph. No.9434261913 SD-2 Roads and Bridges 03.04.2020 02.10.2020 55% Work is in progress Ongoing Works
15 Renovation of Rural Road from NH Road to Mohini house at Rangachang Ward No.- 03 under Zilla Parishad, South Andaman. 14-508/PL/ZP/2022/1720 dt 06.02.2024 ? 5,55,426/- 4-1(1137)/RS/EE/SA/ZP/PB/2022-23 dated 05.07.2024 Shri. Kannan, Govt. Contractor, Anarkali Basti SD-1 Roads and Bridges 08.11.2024 Nil 0% Work not yet started due to rain fall Ongoing Works
16 Repair and maintenance of Rural Road from Muthuswamy Pan Shop to New Bimblitan main road at Bimblitan-02 & 04 under Sippighat Panchayat by Zilla Parishad, South Andaman. 14-602/RR/PL/ZP/2024/1896 dt 06.03.2024 ? 32,58,531/- 4-1(1182)/RS/PB/EE/SA/ZP/2023-24 dated 24.06.2024 (Award letter) M/s Usha Construction Govt. Contractor Brichgunj SD-1 Roads and Bridges 09.07.2024 08.01.2025 0% Work not yet started due to rain fall Ongoing Works
17 Renovation of Rural Road including drain from main road to hindu Graveyard at Calicut ward no.02 (L-120mtrs.) under Zilla Parishad South Andaman 14-591/RR(NP)/PL/ZP/2023/1632 dt 08.01.2024 ?. 8,73,527/- 37/Adhyaksh/ZP/SA/2023-2024 dated 08.03.2024 ? 8,71,816/- Indian Gold Co-operative Society Ltd. SD-1 Roads and Bridges 08.03.2024 07.06.2024 (12.11.2024) date extended vide O/o. No.83 dt. 19.08.2024 5% Road side drain work completed. Work held up due to rain Ongoing Works
18 Construction of Rural road with side drain from Pariswamy to K. Srinivasan house at Calicut W. No. 01 under ZP/SA (L-150.00mtrs) 1(1152)/RS/PB/EE/SA/ZP/2022-23/83 dated 02.03.2023 Rs. 15,54,636/- 1(1152)/RS/PB/EE/SA/ZP/2022-23/903 dated 19/02/2023 ?. 11,39,565.56/- M/s Muthuswamy Dignabad, W.No. 02 near Dignabad school, Port Blair SD-1 Roads and Bridges 05.03.2024 04.06.2024 0% Work awarded Ongoing Works
19 Renovation of C.C road from Anna Nagar PMGSY road to Arumugam house, Rangachang W.NO. 04 under Zilla Parishad, South Andaman. 14-563/RS/PL/ZP/2022/598 dt 14/12/2022 ? 9,71,076/- 20/Adhyaksh/ZP/2023-2024 dated 25.10.2023 Dream Street Constr. Co-operative Society Ltd. Have lock SD-1 Roads and Bridges 25.10.2023 24.12.2023 20% In progress Ongoing Works
20 Renovation of C.C. Road from Burmanallah village road to Shri. A.G. Ponnappan house at Rangachang Ward No. 03 under Zilla Parishad, South Andaman. 14-560/RS/PL/ZP/2022/597 dated 14.12.2022 ?3,52,670/- 14/Adhyaksh/ZP/2023-2024 dated 05.10.2023 ?. 3,26,664/- Udhayam Construction Co-Operative Society Ltd. Burmanallah SD-1 Roads and Bridges 05.10.2023 04.12.2023 0% Work not yet commenced due to non-availability of quarry products. Ongoing Works
21 C/o Rural Road from Quarry road Karnan house to K. Lalitha house at Bimblitan-04 under Zilla Parishad, South Andaman. 14-572/RS/PL/ZP/2023/986 dated 17/04/2023 Rs. 19,22,149/- EE/SA/ZP/2023-24/16 dated 20/11/2023 Rs. 13,64,668/- M/s Haneefa Construction Wimberlygunj, South ANdaman SD-1 Roads and Bridges 20.07.2023 19.01.2024 0% Work not yet commenced due to non-availability of quarry products. Ongoing Works
22 Construction of Rural road from Karuppuswamy house to Govindas house at Bimblitan-03 under Zilla Parishad, South Andaman. 14-570/RS/PL/ZP /2022/692 dated 10/01/2023 ? 28,27,483/- 2-61/EE/ZP/ PB/2022-23/20 dated 10/04/2023 ?. 20,72,342/- M/s Haneefa Construction wimberlygunj, South Andaman SD-1 Roads and Bridges 25.04.2023 26.10.2023 10% In progress Ongoing Works
23 Construction of RCC Box Culvert including earthwork, wing wall & Protection wall near the house of Ramaswamy house in the existing Katcha road from Ayyanar Temple to Shri. Chelleya house at Calicut Ward No.-06 under Zilla Parishad, South Andaman. 14-566/RS/PL/ZP /2022/596 dated 14/12/2022 ?. 40,92,681/- EE/SA/ZP/2022-23/03 dated: 14.03.2023 ?. 24,93,438/- M/s Jagtar Singh & Sons SD-1 Roads and Bridges 29/03/2023 29/09/2023 80% In progress Ongoing Works
24 Repair & Maintenance of Rural Road from main road to ANIIDCO Ice Plant at Ward No. 06 under Govindnagar, Gram Panchayat at Swaraj Dweep by Zilla Parishad, South Andaman (L-420 mtrs). 14-571/RS/PL/ZP/ 2022/681 dt: 06.01.2023 ?. 31,44,689/- EE/ZP/SA/2023-24/7 dt: 30.05.2023 ?. 34,11,344/- M/s Shree Balaji Enterprises MG Road, Middle Point. SD-1 Roads and Bridges 03.05.2023 03.11.2023 90% In progress Ongoing Works
25 Construction of 06 nos. Box Culvert existing roads at near Aboo Plantation at Calicut W.No.V under Gram Panchayat Brichgunj by Zilla Parishad. No. 14-446/RR/PL/ZP/2013/488 dt. 29/05/2013 Rs.33,81,107/- EE/ZP/SA/2014-15/04 dt.19-05-2014 Rs.39,97,836/- M/s Haneefa Construction, Govt. Contractor and Truck Owners Jirkatang, Wimberlygunj, South Andaman Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
26 Construction of Rural Road from Vijay Singh house to mahavir Temple at ward No.06 in Prothrapur by Zilla Parishad, South Andaman No.14-381/RR/PL/ZP/2009/745 dt. 26/07/2012 Rs.28,53,788/- EE/ZP/SA/2014-15/01 dt.21-04-2014 Rs.38,54,13/- Shri Jagtar Singh, Govt. Contractor, Teylerbad. Prothrapur Roads and Bridges 2014-2015 Ongoing Works
27 Repair and Maintenance of Rural Road from main road near Electric transformer to Shri Baikanta Biswas land at Neil Island. No.14-423/RR/NP/PL/ZP/2012/527 dt. 29/05/2012 Rs.10,87,674/- EE/ZP/SA/2011-2012/38 Rs.13,62,729/- M/s N.S.Construction Gurudwara lane, Aberdeen Bazar Prothrapur Roads and Bridges 2014-2015 Ongoing Works
28 Renovation of Zilla Parishad Niwas to Port Blair. 14-93/Genl/PL/ZP/2011/566 dt.17/06/2011 Rs.16,75,215/- EE/ZP/SA/2011-2012/03 Rs.13,00,854/- K.P.Trading and Company Port Blair. Prothrapur Roads and Bridges 2014-2015 Ongoing Works
29 Construction of C.C Road from main road to Kannai Dhali house at Brindadan-II by Zilla Parishad, South Andaman 15-469/RR/PL/ZP/15/43 DT. 19.01.2016 RS. 38,20,082 EE/ZP/SA/16-17/03 DT. 06.05.2016 RS. 30,62,348 Shri. M. Guruswamy, Govt. Contractor, Humfrygunj. Prothrapur Roads and Bridges 2014-2015 Ongoing Works
30 Construction of Rural Road from main road to Burial Ground at Calicut Ward No. 01 under Gram Panchayat Beodnabad "14-482/RR/PL/ ZP/2016/306 dt. 04.04.2016 ` 17,32,153/-" "EE/SA/ZP/2016-2017/10 dt. 22.09.2016 ` 19,07,638/-" Smti. Uma Devi, Govt. Contractor Birchgunj Prothrapur Roads and Bridges 2014-2015 Ongoing Works
31 C/o C.C.drain from Shri Kurma Rao house to Shri Kashya house at ward no.01 under Bambooflat Panchayat by Zilla Parishad. 15-305/RR/PL/ZP/1013/927 dt.11-10-13 Rs.45,25,171/- EE/ZP/SA/2015-16/25 Rs.45,43,050/- A.Palani Govt. Contractor, Bambooflat, South Andaman Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
32 C/o Village Road (Black top) from existing road to K.P.Mani house at Hope Town-II by Zilla Parishad, South Andaman (L-180.00 mtrs) 15-433/RR/PL/2013/776 dt 10-09-2014 Rs.24,09,739/- EE/ZP/SA/@015-16/15 dt.19-10-2015 Rs.36,05,824/- M/s Thirumala Construction, Govt Contractor, Haddo. Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
33 C/o Rural Road from main rad near Ananta Halder house to Suren Das house at Wandoor-I by Zilla Parishad 15-454/RR/PL/ZP/15/473 Rs.45,86,131/- EE/SA/ZP/2015-2016/19 Rs.36,66,830/- Shri T.Abdul Basheer, Govt.Contractor, Mathura Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
34 Repair and Maintenance of of rural road from Surya Chakra main road to Bambooflat Mosque at Ward No. 09 i/c. potholes and repair by Zilla Parishad, South Andaman. 15-526/RR(NP)/PL/ ZP/2017/1094 dt. 13.11.2017 Rs. 27,85,172/- EE/ZP/SA/2017-2018/17 dated 08.12.2017 Rs.23,72,289/- M/s Vetha Construction, Govt Contractor & Supplier, Guru Nanak Market, Port Blair. Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
35 C/o Black top road from Basu Dev Biswas to Chitho Mondal house at Rabindra Nagar under V.K.Pur Panchayat (L-800.00mtrs) 19-77/RR/PL/ZP/14/673 dt.01-08-2014 Rs 45,85,067/- EE/SA/ZP/2017-18/03 Dated 13/09/2017 `20,95,511/- "Shri. A.P. Abdul Aziz, Govt. Contractor, Stewartgunj, South Andaman." Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
36 C/o C.C of Rural along with drain and retaining wall and 01 no Culvert from Panighat dam to Anna Nagar Village road under Zilla Parishad South Andaman 15-492/RR/PL/ZP/2016/1191 DT. 01.12.2016 RS. 32,72,147/- EE/ZP/SA/2016-17/17 DT. 13.02.2017 RS. 39,22,467/- S.K Construction & Engineer, Port Blair Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
37 Black Top Road from main road near Kunjalvi Hajee house to Valaidan House at Ward No-II under Wimberlygunj Panchayat by Zilla Parishad. 15-464/RR/PLZP/2015/827 DT. 19.01.2016 RS. 25,35,512/- EE/ZP/SA/16-17/01 DT. 21.04.2016 RS. 29,38,345/- Shri M. Abdul Hameed, Govt. Contractor, Kanyapuram Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
38 C/o Rural Road from Electricity site office to Shri.O.Mohhammed house at W.No. 08 at Wimberlygunj under ZP, SA "15-455/RR/PL/ ZP/2015/341 dt. 05.05.2015 ` 33,93,366/-" "EE/SA/ZP/2015-16/09 dt. 04.08.2015 ` 28,51,725/-" M/s A.R Construction, Govt. Contractor, Mathura Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
39 Renovation of Rural Road from ATR to Mazar Pahad Caddlegunj-02. "15-493/RR/PL/ ZP/2016/1189 dt. 01.12.2016 ` 30,33,688/- " "EE/ZP/SA/16-17/19 dt. 31.03.2017 ` 36,00,629/-" Universal services near Shiv Shanker Tempal, Bambooflat, South Andaman Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
40 "C/o Wing wall to existing culvert at PMGSY road by Zilla Parishad, South Andaman." "15-495/RR(NP)/PL /ZP/2016/345 dt. 13.04.2016 ` 4,66,140/-" "06/Adhy/ZP/ 16-17 dt. 12.08.2016 ` 5,23,500/-" "M/s Saksham Construction Co- operative Society Ltd, Guptapara" Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
41 Construction of Retaining Wall near Ram Nath house at Caddlegunj-02 by Zilla Parishad, South Andaman. NIC Unique No. 41994 "15-494/RR/Pl/ ZP/16/376 dt. 27.04.2016 ` 10,35,882/-" "EE/ZP/SA/16-17/12 dt. 12.12.2016 ` 12,76,305/-" M/s Haneefa Construction, Govt. Contractor Jirkatang, Wimberlygunj, South Andaman. Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
42 Repair and maintenance or rural road from Muthu Pan Shop to New Bimblitan Church road at Bimblitan 02 & 04 under Sippighat Panchayat by Zilla Parishad, South Andaman. "14-473/RR/PL/ ZP/2016/1188 dt. 01.12.2016 43,48,204/- "EE/SA/ZP/2016-2017/20 dt. 30.03.2017 ` 51,75,639 /-" M/s. Anand Traders & Construction, Govt. Contractor, Bathu Basthi. Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
43 Construction of 06 Nos. Box Culvert existing roads at near Aboo Plantation at Calicut W. No.V under Gram Phanchayat Brichgunj by Zilla Parishad. " 14-446/RR/PL/ ZP/2013/488 dt. 29/05/2013 ` 33,81,107/-" "47/Adhy/ZP/2015-16 dt. 07/08/2015 ` 11,87,056/-" Rural Unemployment Co-operative Society Ltd., Beodnabad. Ferrargunj Roads and Bridges 2014-2015 Ongoing Works
44 Construction of 06 Nos. Box Culvert existing roads at near Aboo Plantation at Calicut W. No.V under Gram Phanchayat Brichgunj by Zilla Parishad. " 14-446/RR/PL/ ZP/2013/488 dt. 29/05/2013 ` 33,81,107/-" "EE/ZP/SA/2014-2015/04 dt. 19/05/2014 ` 39,97,836/-" M/s Haneefa Construction, Govt. Contractor & Truck Owner’s Jirkatang, Wimberlygunj, South Andaman. Ferrargunj Roads and Bridges 2014-2015 Ongoing Works